As part of the AMP6 Thames Water Utilities drive for energy efficiency, Utile were contracted by Edina to provide their 90 and 125 series multistage centrifugal gas booster packages to deliver Biogas to the Edina CHP plants at Bracknell, Wargrave, Camberley, Ryemeads, Slough and Swindon STW sites. With a total contract value exceeding 132K, in partnership with Edina, Utile delivered bespoke equipment compliant to TWUL asset standards as well as IGEM/UP2, ATEX and DSEAR. This incorporated acoustic enclosure’s to maintain a noise level of 65 db’A’ at 1mtr, non-return valves, protection switches, gas line isolation valves and on skid wiring to COMPEX requirements.

Utile’s team of multi skilled and fully certified Gas Safe engineers commissioned the plant and continue to offer aftercare support on these products and many more throughout the Wastewater Industry.