In August 2021 we successfully completed the installation and pressure test of a new ground mount gas holder package for a UK client developing a new industrial application.

Utile were chosen to design, supply and install this Sattler 400m3, Model B9 116/295 ground mounted double membrane as part of a wider scope of supply, to ensure the latest technology was incorporated into the process stream.

Whilst the high quality membrane materials manufactured by Sattler in Germany are the cornerstone to the quality and reliability, Utile have provided all the ancillary equipment to meet the exacting process plant specification and UK industry standards.

New lightening protection masts have been installed to BSEN62305, LPS1 rolling sphere method to ensure the complete installation is protected to the highest safety level.