Contracted by Interserve Construction Ltd, Utile have been awarded the contract to supply and install a 1040m3 Sattler, double membrane gas holder for this food waste processing plant. This will be installed at ground level and be complete with duty standby 7.5kW air blowers as well as our patented inner membrane stabilisation and air distribution system. Installation is scheduled for April 2014 with a view to plant commissioning in the Autumn of 2014. This represents the third gas holder install for Utile in the Food Waste Process industry, following Poplars AD and Reliance St (NMAD), thus strengthening our position in this sector.

Lightning protection masts, designed to BSEN62305 using the rolling sphere method to LPS11 will be supplied and installed by Interserve.