Contracted by Edina once again, Utile designed and built a duty/standby natural gas booster package to supply elevated gas pressure to feed the Edina CHP plant recently installed at the Edinburgh Hospital for Sick Children (EHSC). Using their Utile Model 700 single stage, centrifugal gas boosters, Natural Gas at a flow rate of 150Sm3/hr was boosted up to 50mbarg using 1.1kW WEG, ATEX motors. Acoustic shrouds were fitted to maintain a 65db’A’ noise level and the Utile ‘Smartdrive’ control system was installed with ABB inverters to maintain precise discharge pressure whilst operating at the lowest speed possible, thus reducing the absorbed power to a minimum.