Contracted by J Murphy & Sons, Utile have supplied a double (duty & assist) gas booster package with acoustic enclosures, and all relevant mechanical and electrical protection equipment in accordance with IGEM/UP/2 and CE requirements, for installation in the Alexandra Business Park, St Helens to raise the mains gas pressure to the site. These Utile Model 160/3 multistage stage, centrifugal, Natural Gas boosters with 18.5kW WEG motors will feed up to 3200Sm3/hr of Natural Gas to multiple CHP engines at a pressure lift of 150mbarg to provide back-up power during peak power demand where the grid may not be able to react fast enough.

Delivery to site and fixing down of the package was carried in June 2019 with final connection and commissioning due on Q1 of 2019.