As part of Thames Water Utilities Ltd, AMP6 Capital Delivery, Utile were selected to partner Costain Eight 2 0 to deliver the Biogas boosters for gas transportation to the Boiler and CHP plant forming part of the Basingstoke THP Project.

The scope of works was to design, build, deliver, install, test and commission a duty/standby gas booster package comprising the Model 125/3A centrifugal, multistage gas boosters to deliver a variable gas flow between 300 and 1400Nm3/hr at an elevated pressure of 150mbar(g). All strictly to Thames Water Specifications on time and on budget.

The project was delivered and installed in late 2016 with successful commissioning in January 2017.