This site had a Sattler 1350m3 double membrane gas holder, installed in 1994 therefore boasting over 20 years of trouble free operation. Utile, being the long standing UK sole distributor for Sattler double membrane gas holders were contracted by TWUL direct to provide an exact replacement, as the existing unit was at the end of its design life.

The new installation was complicated by the fact that the site was to remain live at all times and the below ground gas pipes were to be removed and replaced. Utile’s team of skilled design and installation engineers developed a bypass system which was installed under mission critical time lines to ensure process safety and continuity of biogas supply, whilst the new gas holder was erected to the satisfaction of the client.